SHARE
  • Strong amongst German SMEs

    We stand for the values of owner-managed SMEs: reliability, responsibility, quality and adherence to deadlines.

    Georg Jester – General Manager
  • Green Energy Geothermie
  • Focus on our customers

    Professionalism and reliability are what our customers appreciate. And this has been so for over 30 years.

    Andreas Haaß – Managing Director
  • HGÜ HVDC Offshore Sylwin
References   /  WODEGO – Migration of Turbine Controller and Voltage Controller
WODEGO – Migration of Turbine Controller and Voltage Controller

WODEGO – Migration of Turbine Controller and Voltage Controller

Location: Neumarkt, Germany

System/Technology: Siemens S7-300, ABB Unitrol 1010, WinCC, EPLAN Electric P8

Services: Production monitoring, Commissioning, Project management, Quality assurance, Site management, Documentation, As-built status and data recording, Basic-engineering and pre-engineering, Detail engineering, Installation supervision

Industry Branch/Type of Plant: Power Generation, Industrial systems, Power plants

Client: Wodego GmbH, Neumarkt

Tasks

  • Exchange of the existing Symadin turbine controller of a Siemens steam turbine for a S7-300 turbine controller
  • Exchange of the existing Siemens RG3 voltage controller for an ABB Unitrol 1010 voltage controller
  • I&C, electrical engineering and process engineering recommissioning of the turbine

DESCRIPTION OF DELIVERIES AND ACTIVITIES

Software planning

  • Programming the turbine controller in STEP 7 according to the specifications of the existing Symadin software
  • Configuration of the ABB Unitrol voltage controller according to the specifications of the system documentation
  • Adaptation of the WinCC interface

Hardware planning

  • Configuration of the S7-300 hardware and voltage controller
  • Installation planning
  • Documentation of the turbine controller cabinet and the voltage controller cabinet in EPLAN Electric P8

Works test

  • Carrying out the works test in INP Deutschland GmbH
  • Installation and system commissioning of the S7-300 hardware to be supplied
  • 100% signal test (input channel to WinCC) using our own test cabinets
  • Function test of the individual controllers of the turbine controller (speed, power, removal pressure, preliminary pressure) and control limitations on the simulator
  • Logging of results

Installation

  • Carrying out the removal and installation work

Commissioning

  • Writing the commissioning sequence plan and commissioning log
  • Carrying out the commissioning of the turbine and the voltage controller under own responsibility according to the sequence plan and logging the individual commissioning steps

Points of contact

Jürgen Wilkening Prokurist - Business Development Manager

Jürgen Wilkening

PoA - Business Development Manager

INP Deutschland GmbH

Werkstrasse 5

67354 Römerberg

Germany

Tel. +49 6232 6869-0

juergen.wilkeningnoSpam@noSpaminp-e.com

More references

Now, you can discover even more exciting projects and references from the world of INP International Projects.

Competence: Control systems