Harald Knaus
Head of Electrical Engineering
INP Deutschland GmbH
Werkstraße 5
67354 Römerberg
Germany
Tel. +49 6232 6869-0
harald.knaus@inp-e.comvCard
INP International Projects: We offer you
35 years of experience in global power plant, large-scale installation construction and the power industry, combined with the reliability of an owner-managed company.
INP offers you an interesting professional future with bright prospects. Now you can become part of our international team.
INP is your reliable partner in the fields of power generation, transmission and distribution, as well as green energy and construction and infrastructure.
We stand for the values of owner-managed SMEs: reliability, responsibility, quality and adherence to deadlines.
Georg Jester – General ManagerProfessionalism and reliability are what our customers appreciate. And this has been so for over 30 years.
Andreas Haaß – Managing DirectorLocation: Emden, Germany - Conneforde, Germany
System/Technology: 380-kV extra-high voltage level
Services: Commissioning, Project management, Quality assurance, Site management, Documentation, As-built status and data recording, Detail engineering, Installation supervision
Industry Branch/Type of Plant: Transmission & Distribution
Client: TenneT TSO GmbH
Project Size: > € 720 million
The 380-kV grid development project Conneforde – Emden East is necessary for linking offshore grid connection systems (BorWin 3 and 4) and for transmission of the successively rising onshore wind supply from the region.
The two substations Emden/Borssum and Conneforde (Wiefelstede municipality, Ammerland administrative district) have previously been connected to each other via a 2-system 220-kV overhead power line.
The supervision is undertaken by TenneT TSO GmbH. To increase the performance of this connection owing to the increased power generation from offshore wind installations, a renewal of the line route as a 4-system line and increase in the voltage level to 380 kV is necessary. At the same time, the connection is to be routed to the newly erected substation Emden/East. At maximum operational capacity utilization (n-1 case), 3600 A per circuit are to be transmitted.
To optimize your visit on our website we use cookies. Some of them are necessary whereas others are helping us to improve and customize the user experience of our website. For this purpose, cookies are used to collect and analyze pseudonymized data of website visitors. You can at any time change or withdraw your consent from the use of cookies.